Rachel Cooper Roof Replacement (180033)
Project Start and Completion Dates
- Start Date: 8/1/2018
- Completion Date: 10/1/2018
Type of Work
Removing existing built-up roof system and install new EPDM (rubber) roofing system.
Location of Work
Rachel Cooper Roof
Staging Area
The parking are on the East side of the building between Rachel Cooper, Metcalf Elementary School and Fairchild.
Periodic Noise/Odors/Interruptions
- Saws, cranes, noises on the roof and glue.
- The glue fumes according to the manufacturer are not hazardous to your health.
Accessibility, Health, and Safety Notes
- Cranes are being used and materials being removed and brought to the site.
- ADA parking will be located from the staging area to the west side of the building.
ISU Project Manager
Tony Herter
Phone: (309) 438-1927
Notes
This project has a lot of construction activity. Be aware of construction activity around this building.